Army on Track at DLW

17 Jul 2024 Wednesday

News Editor

Our Latest News, Our Latest News

1362

Now that the dust has settled after the election, and rules around purdah lifted, we can tell you all about the hive of activity at DLW at the start of June! In the first weekend in June, 507 STRE (Railway Infrastructure) Royal Engineers...

Read more

A1SLT Signs Armed Forces Covenant

21 Jun 2024 Friday

News Editor

Our Latest News, Our Latest News, Our Latest News

1127

On the evening of Wednesday 12th June, The A1 Steam Locomotive Trust officially signed up to the Armed Forces Covenant. The signatories were AVM Ranald Munro CB CBE TD VR DL, Brigadier Anna Kimber, Captain Will Blackett RN and, from the...

Read more

Tornado Moves to the Great Central

24 May 2024 Friday

News Editor

Our Latest News

1931

On 23rd May, Tornado left the Locomotive Maintenance Services (LMS) works bound for the Great Central Railway (GCR).  Following arrival at the railway, there have been a number of small finishing and snagging jobs to complete, but...

Read more

Our Latest News

Archive

Further progress - July

22 July 2022

Our Latest News

Steady progress continues to be made on multiple fronts to ensure that the locomotive is ready for the return of the wheelsets and boiler.

Overhaul progress - July

18 July 2022

Our Latest News

An update from Locomotive Maintenance Services

Overhaul Extended

30 June 2022

Our Latest News

Tornado is currently undergoing a scheduled major overhaul, something that was planned for completion in June. Unfortunately, due to the impact of covid-19 on industry and manufacturing in...

Spring 2022

31 May 2022

The Communication Cord, The Communication Cord, The Communication Cord

Introducing 21st Century Steam...

25 May 2022

Our Latest News

The A1 Steam Locomotive Trust is delighted to introduce the new name for its railtours business: 21st Century Steam Ltd.

Overhaul over-run explained

13 May 2022

Our Latest News

Tornado’s overhaul programme is running slightly later than expected. This is focussed in three main areas. The boiler will be back around the end of May, rather than the beginning....