New fundraising club 'The Raising Steam Club' already over 50% subscribed! Let’s keep that pressure building! Steam testing the boiler moves another step closer thanks to the people funding the vital fittings needed to bring No....
563
Target reached – thank you! Launched in March, The ADA Clutch Trial and Design Project reached its £15,000 target before the end of May. An incredible response by P2 Supporters! With funding now in place thanks to our generous...
02 March 2021
Mikado Messenger
29 January 2021
08 January 2021
Prince of Wales, Our Latest News
Locomotive frames - With the engine’s frames erected, all the major frame stays, brackets, horn blocks, axle boxes & buffers have been cast and fitted using around 1,000 driven bolts. With the...
01 January 2021
Alan Parkin has now produced several manufacturing drawings for the approximately 140 individual components which are required to fabricate the cylinder block. At the same time David Elliott is...
28 December 2020
With the system design largely complete the Electrical System Specification has been updated to reflect all the new design elements. A start has been made on writing the section on standards...
23 December 2020
Second pair of coupling rods delivered for Britain’s most powerful steam locomotive We are extremely pleased to announce that the second pair of machined coupling rods has been delivered to...