Whilst noting that progress continues elsewhere with both our A1 and P2, the focus in Darlington must be on getting the track down in time for S&D 200 next year and, thanks to our supporters' generous donations to the ballast fund, great...
16 March 2021
Tornado, The Communication Cord, Prince of Wales, The Communication Cord, Highlander, The Communication Cord
02 March 2021
Mikado Messenger
29 January 2021
08 January 2021
Prince of Wales, Our Latest News
Locomotive frames - With the engine’s frames erected, all the major frame stays, brackets, horn blocks, axle boxes & buffers have been cast and fitted using around 1,000 driven bolts. With the...
01 January 2021
Alan Parkin has now produced several manufacturing drawings for the approximately 140 individual components which are required to fabricate the cylinder block. At the same time David Elliott is...
28 December 2020
With the system design largely complete the Electrical System Specification has been updated to reflect all the new design elements. A start has been made on writing the section on standards...