The A1 Steam Locomotive Trust celebrated another major milestone in the construction of Gresley P2 No. 2007 Prince of Wales at its Summer Supporters’ Day, as the locomotive’s three-cylinder monobloc was successfully lowered into the...
Our Latest News, Our Latest News
2369
The A1 Steam Locomotive Trust is pleased to announce the appointment of Paul Roe as a Trustee of the charity and Operations Director. Paul joins the Board bringing extensive operational leadership experience together with a lifelong...
The Communication Cord, The Communication Cord, The Communication Cord
0
28 December 2020
Prince of Wales, Our Latest News
With the system design largely complete the Electrical System Specification has been updated to reflect all the new design elements. A start has been made on writing the section on standards...
23 December 2020
Second pair of coupling rods delivered for Britain’s most powerful steam locomotive We are extremely pleased to announce that the second pair of machined coupling rods has been delivered to...
22 December 2020
Significant progress has been made with all the major components being on hand the first boiler (the spare for Tornado and Prince of Wales) starting to look like a boiler. The boiler for No. 2007...
18 December 2020
Mikado Messenger
Following the initial delivery of motion components from Stephenson (Engineering) Ltd of Atherton work started on machining the four coupling rods. The next steps included the completion of...
15 December 2020
We continue to accumulate brake rigging for the engine, with the two trailing brake hangers and brake stay trial fitted to the frames. The two brake cross shafts have been delivered and Ed Laxton...