Now that the dust has settled after the election, and rules around purdah lifted, we can tell you all about the hive of activity at DLW at the start of June! In the first weekend in June, 507 STRE (Railway Infrastructure) Royal Engineers...
Over £50k raised in under two months, kick starting prototype production
Our Latest News
1684
The A1 Steam Locomotive Trust is building a brand new P2 class steam locomotive, and that project has taken another step towards completion thanks to the generosity of its donors. Just two months after its launch, the Valve Gear Club has raised...
1237
Last week, this eagerly anticipated locomotive took another big step towards completion, as the tender frames which were being manufactured off site were delivered to the Darlington Works. On 12th June, the tender frames for P2 No....
04 September 2023
Mikado Messenger
14 July 2023
Prince of Wales, Our Latest News
General - various events have conspired to affect progress on the P2, mainly associated with the protracted overhaul of and fitment of ETCS equipment to Tornado and the move to our new...
27 June 2023
The Communication Cord, The Communication Cord, The Communication Cord
07 June 2023
Our engineering team of David Elliott and Terry Graham made the long journey to Howco in Irvine to view progress on the P2 cylinder block and to deliver some more items required to blank...
26 May 2023
In a bitter sweet moment, the Trust has this week vacated the historic Carriage Works on Hopetown Lane, Darlington. We left our home of more than 25 years, to move across the tracks to a...