29 March 2021
Prince of Wales, Our Latest News
We are pleased to announce that we have approached five engineering companies to manufacture the complex fabricated cylinder block with responses to our Request for Quotation for Construction...
24 March 2021
We are delighted to announce that the pony truck frame has been delivered to Darlington Locomotive Works (DLW) following its fabrication by North View Engineering Solutions (NVES) in Darlington....
19 March 2021
A new art installation has been unveiled in Darlington to help celebrate the town’s rich railway heritage. The piece of public art takes pride of place on a key route into the town centre, the...
16 March 2021
Tornado, The Communication Cord, Prince of Wales, The Communication Cord, Anon, The Communication Cord
08 January 2021
Locomotive frames - With the engine’s frames erected, all the major frame stays, brackets, horn blocks, axle boxes & buffers have been cast and fitted using around 1,000 driven bolts. With the...
01 January 2021
Alan Parkin has now produced several manufacturing drawings for the approximately 140 individual components which are required to fabricate the cylinder block. At the same time David Elliott is...