News Editor
The Communication Cord, The Communication Cord, The Communication Cord
0
Our Latest News, Our Latest News
397
Whilst noting that progress continues elsewhere with both our A1 and P2, the focus in Darlington must be on getting the track down in time for S&D 200 next year and, thanks to our supporters' generous donations to the ballast fund, great...
3669
Now that the dust has settled after the election, and rules around purdah lifted, we can tell you all about the hive of activity at DLW at the start of June! In the first weekend in June, 507 STRE (Railway Infrastructure) Royal Engineers...
31 January 2020
Mikado Messenger
25 January 2020
Prince of Wales, Our Latest News
On 16th January, a team from Darlington Locomotive Works comprising Graeme Bunker-James, David Elliott and Daniela Filová visited DB Meiningen to view progress on the boilers. All photos by...
13 January 2020
Update on the project to build Gresley class P2 No. 2007 Prince of Wales - Britain’s most powerful steam locomotive We will be holding a series of roadshows across Great Britain in 2020. The A1...
28 December 2019
05 December 2019
Tornado, The Communication Cord, Prince of Wales, The Communication Cord, Highlander, The Communication Cord
The pre-fitting of the tender tank baseplate to the tender frames was completed at Ian Howitt’s works at Crofton near Wakefield where a total of 96 blind nuts were welded to the baseplate. The...