FEATURED STORIES

Autumn 2024

12 Dec 2024 Thursday

News Editor

The Communication Cord, The Communication Cord, The Communication Cord

0

Read more

Autumn tracklaying update

8 Dec 2024 Sunday

News Editor

Our Latest News, Our Latest News

1928

Whilst noting that progress continues elsewhere with both our A1 and P2, the focus in Darlington must be on getting the track down in time for S&D 200 next year and, thanks to our supporters' generous donations to the ballast fund, great...

Read more

Tornado Main Line Return Delayed

9 Sep 2024 Monday

News Editor

Our Latest News

4686

The Trust has made the very difficult decision to cancel ‘The Ribblehead Rambler’ on Saturday 21st September. We apologise wholeheartedly to all those who have been looking forward to traveling with us, especially those who have...

Read more

Our Latest News

Archive

Our Latest News

August ETCS update

09 September 2023

Tornado, Our Latest News

Visits to LMS have seen the completion of key electrical work on the cab.  The most important achievement has been the installation of new wiring boxes under both crew seats, where our wiring...

Supporters' Open Day

05 September 2023

Our Latest News, Our Latest News

Over 200 people came along to the very first Open Day at the new Darlington Locomotive Works on Saturday 5th August. Supporters and their guests braved torrential rain to get the first look at the...

Wheeled Frames and Painted...

05 September 2023

Our Latest News

The last week of August has seen some big milestones hit in Tornado's overhaul. In Loughborough, the driving wheels have been returned to the frames: a significant step fowards! The...

July ETCS update

02 September 2023

Tornado, Our Latest News

The ETCS batteries have been permanently wired up with cable management.  These will be used with the Shore Power Supply to support testing of the tender mounted ETCS components. The...

June ETCS update

09 August 2023

Tornado, Our Latest News

We have continued to make good progress on the electrical aspects of the overhaul and the fitting of ETCS to Tornado.  For ETCS we are working in partnership with SNC-Lavalin and Thales on...

Success! Tornado's boiler...

12 July 2023

Tornado, Our Latest News

After months of frustration and hard work on Tornado's boiler, we are delighted to report that following a successful hydraulic text last week, the boiler today passed its steam test. BES...

123468910Last