We were pleased to welcome the Prime Minister, The Rt Hon Rishi Sunak, and our local MP, Peter Gibson, to Darlington Locomotive Works today. The visit enabled the PM to hear an update on A1 Tornado, P2 Prince of Wales and see the continuing works...
Our Latest News
866
Following completion of a major £1m overhaul A1 class, No. 60163 Tornado will return to the national network this summer, with its first train in June 2024 from the East Midlands and Yorkshire to the iconic Settle and Carlisle...
1350
New build A1 Class locomotive, No. 60163 Tornado, is approaching the end of a major overhaul. The locomotive was committed to visit the Nene Valley Railway (NVR) as its first official engagement at the end of March. Unfortunately,...
30 June 2022
Tornado is currently undergoing a scheduled major overhaul, something that was planned for completion in June. Unfortunately, due to the impact of covid-19 on industry and manufacturing in...
25 May 2022
The A1 Steam Locomotive Trust is delighted to introduce the new name for its railtours business: 21st Century Steam Ltd.
13 May 2022
Tornado’s overhaul programme is running slightly later than expected. This is focussed in three main areas. The boiler will be back around the end of May, rather than the beginning....
08 May 2022
Tornado’s atomisers are in the process of been overhauled at Darlington Locomotive Works (DLW). This is a very small and fiddly but necessary time-consuming job. The atomisers are...
In Loughborough, at Locomotive Maintenance Services, work is continuing to ready Tornado for receipt of the larger components being overhauled in various locations, such as the boiler...
19 April 2022
Steam locomotives are always a challenge in boiler design, and the larger the power output the bigger the challenge. The restrictions of maximum axle load and of the loading gauge (clearance with...