27 December 2020
Tornado, Our Latest News
Our last update saw Tornado just after the locomotive had been repainted in West Coast Railway’s paint shop. On Tuesday 1st September, the day we had been waiting for eventually arrived and No....
23 December 2020
Prince of Wales, Our Latest News
Second pair of coupling rods delivered for Britain’s most powerful steam locomotive We are extremely pleased to announce that the second pair of machined coupling rods has been delivered to...
22 December 2020
Significant progress has been made with all the major components being on hand the first boiler (the spare for Tornado and Prince of Wales) starting to look like a boiler. The boiler for No. 2007...
18 December 2020
Mikado Messenger
Following the initial delivery of motion components from Stephenson (Engineering) Ltd of Atherton work started on machining the four coupling rods. The next steps included the completion of...
15 December 2020
We continue to accumulate brake rigging for the engine, with the two trailing brake hangers and brake stay trial fitted to the frames. The two brake cross shafts have been delivered and Ed Laxton...