24 April 2023
Our Latest News
Last week, we took delivery of the new boiler tubes and stay material for No.60163 Tornado’s boiler. These will be affixed by Northern Steam Engineering Ltd (NSEL) over the coming weeks, and...
18 April 2023
The work on Tornado continues in Loughborough and Darlington. At LMS's works, we are now on the final...
21 March 2023
21st Century Steam Ltd is delighted to introduce a Family Ticket for a table for four on board it’s Aberdonian programme of trains from Edinburgh and Glasgow, offering more affordable...
Rob Morland's team has been making signficant progress installing the Trust element of the ETCS wiring and the tender is now almost complete. Everything is working according to the...
16 March 2023
23 February 2023
It seems like every other month brings another wave of obstacles and difficulties delaying Tornado's return to steam. Following the jubilation on the repatriation of the A1's...