Boiler ordered

21 February 2005

Tornado, Our Latest News

LAST MAJOR HURDLE OVERCOME AS BOILER ORDERED FOR NEW STEAM LOCOMOTIVE Future of mainline steam secure as boiler for No. 60163 Tornado to be completed in June 2006 [caption...

Bond reaches half-way point

28 November 2004

Tornado, Our Latest News

£½ MILLION BOND ISSUE REACHES HALFWAY POINT New steam locomotive on track to be in steam by end of 2007 The A1 Steam Locomotive Trust, the registered charity that is building the first new...

Completion by 2007 possible

17 October 2004

Tornado, Our Latest News

TORNADO TO BE COMPLETED IN THREE YEARS Coal fired No. 60163 in steam by end of 2007 and on mainline in 2008? The A1 Steam Locomotive Trust, the registered charity that is building the first...

Coupling rods fitted

04 October 2004

Tornado, Our Latest News

MAJOR STEP FORWARD AS NEW STEAM LOCOMOTIVE BECOMES A ‘PACIFIC’ Coupling rods fitted to Tornado at Darlington Locomotive Works The A1 Steam Locomotive Trust, the registered charity that is...

Boiler supplier choosen

09 August 2004

Tornado, Our Latest News

MAJOR STEP FORWARD AS BOILER SUPPLIER CHOSEN FOR NEW STEAM LOCOMOTIVE Contract to redesign boiler of No. 60163 Tornado to meet 21st Century requirements agreed The A1 Steam Locomotive...

Bond Issue Launched

31 March 2004

Tornado, Our Latest News

FULL STEAM AHEAD FOR NEW STEAM LOCOMOTIVE BOND ISSUE Haft-million pound 4% unsecured bearer bonds launched to accelerate completion of No. 60163 Tornado The A1 Steam Locomotive Trust, the...