Delays to Tornado's overhaul

28 July 2022

Our Latest News

From the start of the overhaul we have looked forward to Tornado being back in steam this summer. However we have uncovered more components in need of refurbishment and have also faced...

Further progress - July

22 July 2022

Our Latest News

Steady progress continues to be made on multiple fronts to ensure that the locomotive is ready for the return of the wheelsets and boiler.

Overhaul progress - July

18 July 2022

Our Latest News

An update from Locomotive Maintenance Services

Overhaul Extended

30 June 2022

Our Latest News

Tornado is currently undergoing a scheduled major overhaul, something that was planned for completion in June. Unfortunately, due to the impact of covid-19 on industry and manufacturing in...

Introducing 21st Century Steam...

25 May 2022

Our Latest News

The A1 Steam Locomotive Trust is delighted to introduce the new name for its railtours business: 21st Century Steam Ltd.

Overhaul over-run explained

13 May 2022

Our Latest News

Tornado’s overhaul programme is running slightly later than expected. This is focussed in three main areas. The boiler will be back around the end of May, rather than the beginning....